RAMindexFAQ

The 2026 DRAM shortage: why RAM got expensive and when it ends

By Harry Saarinen · Updated

In this guide: 22 sections
  1. Nine causes, in one table
  2. What to do with this on a listing page
  3. US prices rose about fivefold in a year, and DDR4 kits about half as much
  4. Three companies make nearly nine-tenths of the world’s DRAM, all from the same wafers
  5. The shortage was built in the downturn of 2022 and 2023
  6. A gigabyte of HBM costs about three gigabytes’ worth of wafer
  7. Server DDR5 out-earned HBM per wafer in 2026
  8. Allocation, not price, decided who got memory first
  9. DDR4 was squeezed first, by end-of-life notices, and the squeeze ran down to DDR2
  10. A deficit of one or two percent was enough to quintuple the price
  11. Contract, spot, module, retail and used are five prices that do not move together
  12. Retail lagged, overshot, dipped in the spring and climbed again
  13. Used memory is a price you can read directly
  14. PCs, phones and consoles paid in different ways
  15. Servers pay the most per gigabyte, and buyers without contracts pay the margin
  16. Long-term agreements turned a spike into a floor
  17. Record revenue and margins at the suppliers
  18. New fabs take three to five years, and a cleanroom opening is not supply
  19. China’s new capacity is real and mostly spoken for
  20. When it ends: supply in 2028 at the earliest, prices undated
  21. What would end it sooner, and what would make it last
  22. Questions people ask, answered in brief

RAM got expensive because the three companies that make nearly nine-tenths of the world’s DRAM gave their wafers to AI data centers first, as HBM for the accelerators and as server DDR5 for the machines around them. On the dated supply outlooks available in mid-October 2026, new fabs ramp meaningfully only from the second half of 2027, and the gap does not close before 2028. In the US a mainstream 32GB DDR5-6000 kit averaged $572 in August 2026 against $108 a year earlier, on PCPartPicker’s figures as compiled by Tom’s Hardware, and TrendForce’s quarterly contract figures compound to about five times their mid-2025 level. Micron, the largest US memory maker, said on September 30, 2026 that it expects conditions “much tighter in calendar 2027 and 2028 than they were in 2026”, and none of the forecasts collected here dates a return to 2025 prices.

Evidence as of November 12, 2026: Micron’s fiscal fourth-quarter results of September 30, TrendForce’s fourth-quarter contract forecast of September 30 and its spot prices of October 15 and November 12, and the third-quarter results of SK hynix (October 28) and Samsung (October 29). Trends shows how this site’s like-for-like price per gigabyte has moved since October 3, 2026.

Nine causes, in one table

“AI ate the RAM” is the usual explanation, and it is incomplete. The DDR4 squeeze began in mid-2025, before AI-server buying reached ordinary memory; from early 2026 an ordinary server module earned more per wafer than HBM; and a deficit of 1% to 2% of bits produced roughly a fivefold rise in contract prices. Each row links to its section.

Cause What happened Evidence, dated
Three suppliers, one kind of wafer Samsung, SK hynix and Micron took 87.6% of DRAM revenue in 2Q26; HBM, server DDR5 and desktop DDR5 come off the same wafers TrendForce, Sep 7, 2026
No slack after the 2022-23 downturn output cuts and losses, then inventory fell from 13-17 weeks in late 2024 to 2-4 weeks in October 2025 TrendForce data via Reuters, Dec 2025
HBM eats wafers HBM took 18% of the big three’s DRAM wafer input at the end of 2025 but supplied 8% of DRAM bits Micron, Dec 2025; TrendForce, Jun 2, 2026
Server DDR5 out-earned HBM a 64GB DDR5 RDIMM made more per wafer than HBM from 1Q26; HBM and RDIMMs take 51% of 2026 bit supply TrendForce, Jun and Aug 2026
Allocation cloud providers bought 2026 supply in late 2025; large module makers received 30-50% of the chips they asked for TrendForce; Commercial Times, Jan 2026
DDR4 end-of-life end-of-life notices in mid-2025; a DDR4 8Gb chip cost 15.1 times its early-June 2025 spot price on November 12, 2026 TrendForce
Buyers who barely respond to price a 1-2% bit deficit met cloud providers whose capital spending is projected to rise 106% in 2026, to $957 billion TrendForce, Jul 30 and Oct 14, 2026
Contract floors Micron’s 26 long-term agreements cover over 35% of its revenue through 2030, and SK hynix’s more than half of its 2027 and 2028 capacity Micron, Sep 30, 2026; SK hynix, Oct 28, 2026
Slow new fabs three years “if you’re rushing”, four or five to ramp a new fab; meaningful ramps from 2H27, substantial output in 2028 TechInsights, Dec 2025; TrendForce, Jul 2026

Every cause is on the supply side or in who buys first, so a dip in one shop is not the end of the shortage; an end needs new fabs to ramp or AI spending to fall. The dated forecasts are in when it ends.

What to do with this on a listing page

  1. Read the view’s cheapest and median price per gigabyte, not one kit. The gap between them is the market’s spread.
  2. Compare generations per gigabyte on every generation by price per gigabyte, or on DDR5, DDR4 and DDR3, before assuming the older one is cheaper.
  3. Watch the direction on Trends, which keeps a like-for-like price per gigabyte for each generation from Buy It Now listings, new and used together.
  4. Compare Buy It Now prices, the default view, because a bid is not a price. ?bids=show adds bid-only auctions, and ?auctions=no removes auctions altogether.
  5. For servers, expect the RDIMM premium. Compare DDR5 registered with DDR5 desktop per gigabyte, and DDR5 server with DDR4 registered for the generation gap.
  6. Use part pages to compare one part number across sellers and conditions, and test used modules as buying used RAM on eBay describes.
  7. Re-read the page on the day you buy. Its prices move daily, and this guide links to them rather than quoting them.

If the machine is needed now, waiting has no dated reward: no supply forecast expects relief in 2026. If the current machine works, the case for waiting rests on supply in 2028, not on a dip. The full decision is in buy RAM now or wait; size the purchase with how much RAM you need, and confirm the machine first with how to check what RAM fits or the table of server models.

US prices rose about fivefold in a year, and DDR4 kits about half as much

The plainest US measure is PCPartPicker’s average price for the same kits a year apart, compiled by Tom’s Hardware on August 17, 2026:

Kit, PCPartPicker US average August 2025 August 2026 Multiple (worked) Per GB (worked)
DDR5-6000 2x16GB $108 $572 5.3 $3.4 to $17.9
DDR5-5600 2x32GB $191 $1,118 5.9 $3.0 to $17.5
DDR4-3200 2x16GB $105 $281 2.7 $3.3 to $8.8
572 / 108 = 5.30       1,118 / 191 = 5.85       281 / 105 = 2.68
dollar rise in a year:  DDR5 32GB +$464    DDR5 64GB +$927    DDR4 32GB +$176

Because the shortage behaves as a charge per gigabyte, buyers who need the most, for workstations, virtual machines or local AI models, carry the largest dollar rises. DDR4 kits rose about half as much as DDR5 kits, although DDR4 chips cost more per bit at spot. Module makers stocked DDR4 in early 2025 (TrendForce, September 22, 2026), and lower-grade DDR4 chips trade at about half the per-gigabyte price of lower-grade DDR5, two likely reasons for the gap. Whether DDR4 is a way around the shortage is the subject of is DDR4 still worth buying.

Contract prices, what PC makers, phone makers and cloud providers pay the suppliers, tell the same story. TrendForce publishes the only public quarterly series for “conventional DRAM”, all DRAM except HBM. Multiplied out:

4Q25 and 1Q26 measured, 2Q26 and 3Q26 forecast, as multipliers
midpoints    1.475 x 1.955 x 1.605 x 1.155 = 5.35
low ends     1.45  x 1.93  x 1.58  x 1.13  = 5.00
high ends    1.50  x 1.98  x 1.63  x 1.18  = 5.71

retail check: PCPartPicker average, DDR5-6000 2x16GB (via Tom's Hardware)
             August 2025 $108 -> August 2026 $572     572 / 108 = 5.30

Two of the four quarters are forecasts, so 5.35 is a forecast-weighted estimate, not a measured index; the retail check is independent and lands in the same place.

Compounded, TrendForce's figures put DRAM contract prices at about five times their 3Q25 level by 3Q26 Index, 3Q25 = 100, conventional DRAM, compounded from TrendForce's quarterly changes
Forecast01002003004005006003Q254Q251Q262Q263Q26

Sources: TrendForce, Feb 26, 2026 (4Q25: +45-50%); TrendForce, Jun 1, 2026 (1Q26: about +93-98%); TrendForce, Mar 31, 2026 (2Q26 forecast: +58-63%); TrendForce, Jul 3, 2026 (3Q26 forecast: +13-18%, repeated Sep 7). 2Q26 and 3Q26 are TrendForce forecasts. Each quarter uses the midpoint of TrendForce's range: 1.475 x 1.955 x 1.605 x 1.155 = 5.35.

Show the figures
Compounded, TrendForce's figures put DRAM contract prices at about five times their 3Q25 level by 3Q26 (Index, 3Q25 = 100, conventional DRAM, compounded from TrendForce's quarterly changes)
PeriodConventional DRAM contract price
3Q25100
4Q25147.5
1Q26288.4
2Q26462.8 (forecast)
3Q26534.6 (forecast)

TrendForce’s first forecasts kept missing low. For the fourth quarter of 2025 it first forecast +8% to +13% and measured +45% to +50%; for the first quarter of 2026 it first forecast +55% to +60% and measured about +93% to +98%, nearly three times the previous single-quarter record of about 35%. Read any upward forecast from this period as a floor rather than a central estimate.

Early October brought a plateau, not a turn. TrendForce’s spot report of October 7 said chip prices were “moving sideways”, with the DDR4 8Gb chip unchanged at $46.32, and its bulletin the same day said that at Micron “contract price momentum is easing”. Its forecast of September 30 still has conventional DRAM contract prices rising 10% to 15% in the fourth quarter, slower than the third quarter’s 13% to 18% but a climb, with server DRAM “expected to remain undersupplied”. Micron’s DRAM prices rose by a high-teens percentage in its quarter to September 3 (Micron, September 30, 2026).

Three companies make nearly nine-tenths of the world’s DRAM, all from the same wafers

DDR4 and DDR5 desktop modules, the LPDDR5X soldered into phones and thin laptops, the GDDR on a graphics card and the HBM stacked beside an AI accelerator are all DRAM. They are different dies with different interfaces, which is what DDR4 vs DDR5 is about. For supply they are one thing: they come off the same kind of 300 mm silicon wafer, in the same few companies’ fabs, and a wafer started as HBM is a wafer not started as anything else. IDC put it bluntly in December 2025: “This is a zero-sum game: every wafer allocated to an HBM stack for an Nvidia GPU is a wafer denied to the LPDDR5X module of a mid-range smartphone …”

TrendForce’s revenue ranking for the second quarter of 2026, published on September 7, shows who controls the wafers:

Supplier 2Q26 DRAM revenue Share of industry Change on 1Q26
Samsung $60.98 bn 39.4% +63.4%
SK hynix $38.59 bn 24.9% +37.9%
Micron $36.00 bn 23.3% +65.5%
CXMT not in the ranking release 9.5% (TrendForce news desk, Sep 24, 2026) share up from 7.6%
Nanya $2.612 bn 1.7% (worked here) +68.3%
Winbond $0.998 bn 0.6% (worked here) +75.8%
PSMC $0.115 bn 0.1% (worked here) +167.8%
Whole industry $154.73 bn 100% +59.5%
60.98 + 38.59 + 36.00 = 135.57
135.57 / 154.73       = 0.876   -> 87.6% of DRAM revenue, 2Q26
87.6% + CXMT's 9.5%   = 97.1%   -> the top four

A figure of “about 95%” for the big three is widely repeated; TrendForce’s latest quarterly revenue data says 87.6%. Counterpoint’s count for the third quarter of 2026 (November 5, 2026) puts Samsung at 38%, SK hynix at 29% and Micron at 21%, together 88%, and CXMT at 9%. Nanya, Winbond and PSMC in Taiwan are the companies still making DDR4, DDR3 and DDR2 in volume, and their growth rates in the last column are the legacy-memory story in one line. A market in which three sellers hold nearly nine-tenths of supply answers a jump in demand with price rather than volume whenever capacity is fixed, and in 2025 and 2026 capacity was fixed.

The shortage was built in the downturn of 2022 and 2023

The precondition was a glut. In late September 2022 Micron became the first major memory maker to announce an official cut to its DRAM and NAND output (TrendForce, October 3, 2022). DRAM industry revenue fell 21.2% in the first quarter of 2023, to $9.663 billion, the third straight quarterly decline (TrendForce, May 25, 2023), and Micron’s gross margin was minus 32.6% in the quarter to March 2, 2023. Two habits carried into 2024: caution about new capacity after the losses, and a steering of advanced capacity toward HBM. TrendForce warned on May 20, 2024 that “The increased focus on HBM production could lead to a DRAM supply shortage.” DRAM revenue fell for the last time in the first quarter of 2025, by 5.5%. Then the stock ran out:

When Average DRAM inventory Source
Late 2024 13-17 weeks TrendForce data via Reuters
July 2025 3-8 weeks TrendForce data via Reuters
October 2025 2-4 weeks TrendForce data via Reuters
November 2025 suppliers’ stock “almost depleted” TrendForce, Nov 26, 2025
September 2026 suppliers’ stock “at historic lows” TrendForce, Sep 7, 2026

The report does not say whose inventory the weeks measure, so read the column as a direction. The rally started from a price trough only about a year before the spike, with the industry’s spare stock gone and no cleanroom space standing empty. Worked from TrendForce’s figures, quarterly DRAM revenue rose about sixteenfold in 13 quarters (154.73 / 9.663 = 16.0), and almost none of that is volume.

A gigabyte of HBM costs about three gigabytes’ worth of wafer

High-bandwidth memory is DRAM dies stacked vertically, joined by through-silicon vias (TSVs), and packaged beside an accelerator, the stacking idea of the 3DS server modules in ranks and 3DS modules at a far larger scale. TrendForce wrote in March 2024 that an HBM die is 35% to 45% larger than a DDR5 die of the same process and capacity, its yield 20% to 30% lower including the TSV packaging, though TrendForce’s May 20, 2024 release gave different figures, so read both as estimates. Micron’s prepared remarks for its December 2025 results give one number: “the 3-to-1 trade ratio with DDR5, and this trade ratio only increases with future generations of HBM”. That is a supplier’s figure, so here is a check from TrendForce’s estimates of June 2, 2026: HBM’s share of the big three’s DRAM wafer input, against its share of DRAM bit supply.

HBM takes more than twice the share of DRAM wafers that it supplies in bits % of DRAM wafer input and of DRAM bit supply going to HBM, at year end, TrendForce estimates
Forecast0%10%20%30%End 2025End 2026End 2027

Source: TrendForce, Jun 2, 2026. End-2026 and end-2027 figures are forecasts. The wafer share covers the three largest makers; TrendForce does not say whether the bit share does too.

Show the figures
HBM takes more than twice the share of DRAM wafers that it supplies in bits (% of DRAM wafer input and of DRAM bit supply going to HBM, at year end, TrendForce estimates)
PeriodShare of the big three's DRAM wafer inputShare of DRAM bit supply
End 202518%8%
End 202622% (forecast)9% (forecast)
End 202730% (forecast)13% (forecast)

Worked here rather than by TrendForce, those shares imply that a wafer of conventional DRAM yields about 2.5 to 2.9 times the bits of a wafer of HBM: at the end of 2025, (92 / 82) / (8 / 18) = 2.5. That agrees with Micron’s three to one. If the bit share covers the whole industry rather than the big three alone, the ratio is lower, about 2.2 to 2.5, so read the range as roughly two to three.

The amount of HBM per accelerator keeps rising, too: TrendForce’s June 2026 release has it going from 96GB and 192GB to 216GB and 288GB per AI chip during 2026, and Nvidia’s Rubin Ultra expected at 384GB per GPU in 2027, though by August TrendForce reported Nvidia weighing lower configurations because of the 2027 shortage. A gigabyte of HBM does not remove a fixed number of desktop gigabytes; the trade is in wafers, and in 2026 the wafers HBM did not take went mostly to server DDR5, not desktop kits.

Server DDR5 out-earned HBM per wafer in 2026

HBM is priced once a year, conventional DRAM every quarter. Nvidia opened its 2026 HBM3E negotiations in May 2025, while buyers still had leverage, and locked prices in before the market turned (TrendForce, December 18, 2025). In October 2025 TrendForce forecast that “DDR5 profitability is projected to surpass that of HBM3e starting in the first quarter of next year”, and in June 2026 it reported the outcome: “HBM wafer revenue was overtaken by DDR5 64GB RDIMM in 1Q26”. Once the commodity server module paid better per wafer than HBM, no supplier had a reason to release wafers from either to make desktop memory. That module is the part listed under DDR5 registered and DDR5 64GB modules here; server RAM vs desktop RAM explains why it will not run in a desktop board.

Demand for ordinary RDIMMs widened at the same time. Cloud providers extended their buying from AI servers to general-purpose ones, “to RDIMMs across multiple densities” (TrendForce, February and June 2026), and agentic-AI inference raised the number of CPUs per GPU from 1:8 toward 1:4 or higher (TrendForce, May 29, 2026), each CPU with its own DDR5. TrendForce estimated in August 2026 that HBM and RDIMMs together take 51% of all DRAM bit supply in 2026. Phone-class memory joined the queue: on the suppliers’ preliminary 2027 plans, Nvidia would get only about 60% of the LPDRAM it needs (TrendForce, June 2026).

The much-repeated claim that OpenAI consumes 40% of the world’s DRAM comes from Samsung’s non-binding letter of intent with OpenAI of October 1, 2025, which put OpenAI’s memory demand at “up to 900,000 DRAM wafers per month”. It is a projection, not a measure of consumption.

Allocation, not price, decided who got memory first

The queue formed in the fall of 2025. TrendForce reported on September 24, 2025 that some US cloud providers planned to start 2026 procurement “as early as 4Q25, adopting a more flexible stance on pricing”. SK hynix said on October 29, 2025 that customers had already taken its entire 2026 DRAM and NAND production, and Micron’s December 2025 remarks were blunter: “Despite significant efforts, we are disappointed to be unable to meet demand from our customers, across all market segments.”

Place in the queue Buyer What was reported in 2025-26 Source
1 US cloud providers with long-term agreements (LTAs) bought 2026 supply from 4Q25; rises capped from 3Q26 TrendForce, Sep 2025 and Jul 2026
2 Other cloud providers, including Chinese ones 2026 capacity “nearly sold out” to US and Chinese cloud service providers (CSPs) Commercial Times, Jan 2026
3 Server OEMs allocation below requests; quote validity cut TrendForce; The Register, Feb-Mar 2026
4 PC and phone brands most receiving 50-70% of planned supply Commercial Times, Jan 2026
5 Module makers large ones receiving 30-50% of requested chips; 2027 supply possibly 30% of 2026’s Commercial Times; Apacer’s CEO, Jul 2026
6 Retail and system builders whatever the module makers can build no published measure
7 The second-hand market modules released from earlier purchases no published measure

The second half of row five is an executive’s view: Apacer’s chief executive C.K. Chang said on July 24, 2026, as DigiTimes and Tom’s Hardware reported, that big-maker supply to independent module makers could fall in 2027 to about 30% of the 2026 volume. Every retail DIMM and SODIMM comes from a module maker, and Kingston alone held 62% of module-maker revenue in 2025 (TrendForce, September 22, 2026). The retail kit is the last link in a queue whose first buyers barely look at price.

The best-known casualty was a brand: on December 3, 2025 Micron announced that it would leave the Crucial consumer business, shipping through the consumer channel until February 2026, “to improve supply and support for our larger, strategic customers in faster-growing segments”. Warranty service continues; what that means for a claim is in is DDR4 still worth buying.

DDR4 was squeezed first, by end-of-life notices, and the squeeze ran down to DDR2

The oldest mainstream generation went up first. TrendForce’s release of June 5, 2025 gives the reason: “Given the significantly higher profit margins for HBM, DDR5, and LPDDR5(X), suppliers have laid out EOL plans for DDR4, with final shipments expected by early 2026.” Tariffs added a rush, as OEMs front-loaded shipments before the grace period on April’s US reciprocal tariffs expired on July 9. The reported exit dates moved, Samsung’s and SK hynix’s into 2026, and CXMT was reported to have ended most of its DDR4 by late 2025.

On June 23, 2025 the DDR4 16Gb chip averaged $12.00 at spot against $6.01 for DDR5 16Gb, “a first in DRAM history”, in the words of TrendForce’s news desk. Nearly seventeen months later the inversion still held, on TrendForce’s spot table of November 12, 2026:

DDR4 16Gb 3200 chip  $79.75        DDR5 16Gb 4800/5600 chip  $60.233
79.75 / 60.233 = 1.32   -> DDR4 chips about 32% more expensive per bit than DDR5 chips
DDR4 8Gb chip:  $2.963 (early June 2025) -> $44.714 (Nov 12, 2026) = 15.1 times

Nothing replaced the lost supply. Micron’s new Virginia DDR4 serves long-lifecycle customers only and reflects internal reallocation (TrendForce, May 2026), and the Taiwanese makers who took the business cannot “fully offset the reduction in supply”, TrendForce said in July. Then the cascade: in March 2026 DDR3 and DDR2 prices rose 20% to 40% in a month (TrendForce, April 7, 2026), by June some OEMs were redesigning DDR4 products onto DDR3 and DDR3 products onto DDR2, and TrendForce forecast DDR2 contracts up 55% to 60% in the second quarter and 35% to 40% in the third.

DDR2 contract, 2Q26 x 3Q26 forecasts at midpoints:  1.575 x 1.375 = 2.17
  -> more than doubled in two quarters, if the forecasts held
DDR3 4Gb chip = 0.5 GB:   13.777 / 0.5 = $27.6 per GB (Nov 12, 2026), close to DDR5's $30.1

DDR3 and DDR2 rose last and sometimes hardest, because nobody is building capacity for them. The DDR3, DDR3 server, DDR2 and original DDR listings here are priced by the same per-gigabyte measure as DDR4 and DDR4-3200.

A deficit of one or two percent was enough to quintuple the price

Readers meet several different “shortage” numbers, and they measure different things:

Figure Who and when What it actually measures
-1% to -2% TrendForce, Jul 30, 2026 2026 DRAM bit sufficiency for the whole market; the gap widens in 2027
more than 20% SK Group chairman Chey Tae-won, Mar 2026 (Bloomberg) wafer supply against demand, from a supplier’s parent
16% IDC, Dec 2025 2026 DRAM supply growth in bits
low-to-mid 20s % Micron, Jun 2026 2026 industry DRAM bit shipment growth
mid-20s % SK hynix, Jul 2026 (call transcript) 2026 DRAM demand growth
4.8% a year SEMI, Feb 2026 wafer capacity growth to 2030
51% TrendForce, Aug 25, 2026 HBM and RDIMM share of 2026 bit supply

IDC’s 16% and Micron’s low-to-mid 20s disagree about supply growth, and were made six months apart. An illustration shows the sizes are at least coherent; it is not how TrendForce computes its ratio:

demand +25% (SK hynix, "mid-20%")    supply +23% (Micron, "low- to mid-20s")
1.23 / 1.25 = 0.984   -> a deficit of about 1.6% of bits

So small a gap produced so large a price because of who sits at the margin. TrendForce estimated on October 14, 2026 that the nine leading cloud providers (Google, Amazon, Meta, Microsoft, Oracle, ByteDance, Tencent, Alibaba and Baidu) would raise their capital spending 106% in 2026, to $957 billion, and a further 60% in 2027, to more than $1.5 trillion. On August 25 it put DRAM and NAND at 47% of major cloud providers’ capital spending in 2026 and 68% in 2027. In February 2026 it explained why this cycle differs from the last: “CSP procurement volumes are growing exponentially, and their relatively lower sensitivity to pricing has enabled record-high price increases exceeding those seen in the previous supercycle.”

A PC maker facing a doubled memory bill can cut the specification, raise the price or ship fewer machines, and in 2026 it did all three. A cloud provider racing to build AI capacity has one alternative to paying, which is not building, and through 2026 it chose to build. When the buyer at the margin will pay almost anything, the price is set by the last bit, not the average one, and everyone further down the queue pays the price that buyer set.

Contract, spot, module, retail and used are five prices that do not move together

Contract prices are negotiated between makers and OEMs or cloud providers, quarterly or monthly, and carry most of the volume. Chip spot is daily broker trading in single chips, “only a small fraction of total memory sales” in TechSpot’s words. Module spot is weekly trading in finished modules, retail is new kits on shelves, and used has no published series at all. Mind the units: TrendForce’s “DDR4 16Gb (2Gx8)” is a 16-gigabit chip holding 2 gigabytes, and a widely repeated April 2026 figure for “a 16GB DDR4 chip” at $74.10 was that 2GB part. Every layer normalized to dollars per gigabyte, at the latest figure checked, dated in the table:

Layer Example and date Per GB (worked) Source
Chip spot, branded DDR5 16Gb $60.233; DDR4 16Gb $79.75 (Nov 12, 2026) $30.1; $39.9 TrendForce spot table
Chip spot, lower grade (eTT) DDR5 16Gb $27.80; DDR4 16Gb $14.113 (Oct 15, 2026) $13.9; $7.1 TrendForce spot table
Module spot DDR5 UDIMM 16GB $243.333; DDR4 UDIMM 16GB $164.20; DDR5 RDIMM 32GB $2,025 (updated Nov 2, 2026) $15.2; $10.26; $63.3 TrendForce module table
Contract module DDR5 8GB SO-DIMM $130; DDR4 16GB SO-DIMM $265 (second half of July) $16.3; $16.6 TrendForce contract table
OEM cost or OEM-quoted price DRAM price quoted by Dell, $2.39 per gigabit (Feb); Framework DDR5 SO-DIMM cost (Mar); Raspberry Pi inventory average (Jun 30) $19.1; $13-18; $13.3 The Register; Framework; The Register
Retail, best price DDR5-6000 32GB $409; DDR4-3200 32GB $190 (Sep 14) $12.8; $5.9 Tom’s Hardware tracker
Retail, average DDR5-6000 2x16GB $572; DDR4-3200 2x16GB $281 (Aug) $17.9; $8.8 PCPartPicker via Tom’s Hardware
per GB = price / gigabytes; a 16Gb chip holds 2 GB:  60.233 / 2 = 30.1 $/GB
module spot, DDR5 RDIMM 32GB:  2,025 / 32 = 63.3 $/GB
Dell's quote:  2.39 $/Gbit x 8 bits per byte = 19.12 $/GB

A branded DDR5 chip on the spot market costs more than twice as much per gigabyte as the cheapest retail kit, and a DDR4 chip more than six times as much. Chip spot is thin and disorderly: on October 15, 2026 the DDR4 16Gb chip traded between $45.60 and $118.00 within one session. Modules are not built from spot chips at the day’s price, since TrendForce credits module makers’ profits to low-cost inventory built in 2024 and 2025. And retail sells stock bought months earlier; one Lexar manager told Tom’s Hardware in June 2026 that costs take up to eight to nine months to reach consumer prices.

A price is most useful with its layer and its date. Every listing page here adds a sixth vantage point, listed modules at the moment you look, with the cheapest and median price per gigabyte: every generation by price per gigabyte, DDR5 16GB modules, DDR4 16GB modules and DDR5 registered correspond to the rows above.

Retail lagged, overshot, dipped in the spring and climbed again

Shelf prices followed the contract series with a delay, ran ahead of it, then paused. A best price, an average and one kit’s price are different things, so each row says which it is.

Date Figure What it measures Source Per GB (worked)
Aug to early Nov 2025 Crucial Pro 32GB DDR5 $83 to $170; Kingston Fury Beast 32GB $123 to $288 two kits PC Gamer, Nov 6, 2025 $2.6 to $5.3; $3.8 to $9.0
Mar 2026 DDR4 and DDR5 16Gb chip spot down about 5% in a month, DDR4’s first monthly fall since Feb 2025; some 32GB DDR5 kits in Chinese channel listings and on Amazon down as much as 30% chip spot; channel and retail kits DigiTimes via Tom’s Hardware and TechSpot, Apr 10 not applicable
Aug 2026 DDR5-6000 2x16GB average $572, best $392 average and best Tom’s Hardware, Aug 17 $17.9; $12.3
Sep 14, 2026 best DDR5-6000 32GB $409 best Tom’s Hardware tracker $12.8

The explanations given for the spring dip were about inventory, not supply. IDC’s Tom Mainelli told PCWorld in April that “some SKUs saw pricing rise above what the market would support”, adding that “we are still far from normalization”, and DigiTimes, as relayed by TechSpot on April 10, named two causes: distributors who had stockpiled at the start of the rally selling their inventory, and Google’s TurboQuant announcement prompting some to clear stock. On August 24 the cheapest 32GB DDR5-6000 kit crossed $400 (Tom’s Hardware).

August 2026:  572 average / 392 best = 1.46  -> the average kit cost 46% more than the cheapest
DDR5 16Gb spot:  $37.20 (early April, TechSpot) -> $60.433 (Oct 15, TrendForce) = +62%

European shops show the same shape. 3DCenter’s index of the cheapest German retail offer (July 2025 = 100) had DDR5 at 408 in March 2026 and 544 in September, and ComputerBase found German desktop kits 370% more expensive on September 16, 2026 than a year earlier. A dip in one layer, in one region, for one kit, is inventory moving, not supply arriving. The DDR5 kits totaling 32GB and DDR5-6000 pages state both the cheapest and the median price per gigabyte.

Used memory is a price you can read directly

Two small indices of street prices come closest to a published used-price series:

Source What it measures What it shows Caveat
eRacks, Sep 22, 2026 median of its daily lowest street prices, March to September 2026 DDR4 RDIMM $7.44 to $5.56/GB (-25%); DDR4 desktop -13%; DDR5 RDIMM $24.37 to $31.05/GB (+27%); DDR5 desktop +20% a server seller’s own tracking; new or used not stated
DatacenterDisk, Sep 2026 medians of server-memory listings on Amazon US DDR4 ECC $9.34/GB; DDR5 ECC $41.09/GB 25 DDR4 and 16 DDR5 modules; DDR5 new stock only, DDR4 includes refurbished

The two small indices agree that in September 2026 DDR4 server memory sold for about a fifth of DDR5 server memory per gigabyte (5.56 / 31.05 = 0.18; 9.34 / 41.09 = 0.23), the opposite of chip spot, where DDR4 is the more expensive silicon. Neither is a used-price index in the strict sense, and neither is eBay.

Meta now reuses 32GB DDR4 modules recovered from decommissioned servers in new servers, through its own CXL chip (The Register, June 29, 2026), which may mean fewer ex-data-center modules reach resale. And recovered chips are traded: TrendForce’s spot report of September 16 noted that “reballed chips sustained the upward price momentum”, one reason provenance matters.

Trends adds the direction: since October 3, 2026 it has kept a like-for-like price per gigabyte from Buy It Now listings, new and used together. Pages such as DDR4 registered rank listings by price per gigabyte and show condition per listing, and buying used RAM on eBay covers how to test what arrives.

PCs, phones and consoles paid in different ways

HP said in late February 2026 that memory had risen to about 35% of the cost of materials for a PC, from 15% to 18% the quarter before. TrendForce put the CPU, DRAM and SSD at about 45% of a $900 notebook’s bill in 1Q25 and 68% by 3Q26, and estimated on September 4, 2026 that the notebook would need a price about 80% higher to keep its 1Q25 margin. On October 8, 2026 it projected global notebook shipments down by a low-single-digit percentage in 2027, and by a high-single-digit percentage if brands pass the full cost on.

Apple raised Mac and iPad prices on June 25, 2026, the 13-inch MacBook Air from $1,099 to $1,299, saying it had “never seen a component price increase this much, this quickly”, and in May had dropped the $599 Mac mini, leaving $799 as the entry model (CNBC, June 25, 2026). The cheap configuration is what disappears: a laptop at 2025’s price now tends to carry less memory, and one with the same memory costs more. High-end thin laptops with soldered memory were the segment most prone to early price pressure, TrendForce said in December 2025, because they “cannot reduce costs by lowering specifications or replacing modules”; whether a laptop can take more memory later is in how to check what RAM fits, and the modules are under DDR5 laptop and DDR4 laptop.

US buyers carry one extra layer, tariffs. IDC wrote in February 2026 that a 10% across-the-board tariff had replaced the reciprocal tariffs the Supreme Court struck down. It took effect on February 24 and lapsed on July 24, 2026, replaced the same day by duties of 10% or 12.5% on imports from about 60 economies, with exemptions (Holland and Knight, July 30, 2026). Whether a given module or PC is exempt depends on its classification and origin.

Phones and consoles paid too. TrendForce forecast phone LPDDR5X contracts up 78-83% in 2Q26 (May 14, 2026); the Steam Machine launched at $1,049 against the $700-800 Ampere Analysis had expected (BBC, June 23, 2026); and the 16GB Raspberry Pi 5 went from $120 at launch to $305. Raspberry Pi published its average memory inventory cost, $3.60 per gigabyte at the end of 2025 and $13.30 at the end of June 2026 (The Register, September 25, 2026), so 16 GB x $9.70 = $155 explains nearly all of the $160 rise since its December 2025 price of $145, though the two periods overlap rather than match. GDDR7 shortages delayed Nvidia’s RTX 5000 Super (TechSpot, August 15, 2026). Flash is on a different path, with TrendForce expecting NAND to loosen in the second half of 2027 while DRAM stays tight; drive prices are covered in the sister site’s storage price guide and listed on its SSD, NVMe and hard drive pages.

Servers pay the most per gigabyte, and buyers without contracts pay the margin

Server memory rose further and for longer than desktop memory:

Measure Figure Source and date
Server DRAM contract, 2H25 +64% cumulative TrendForce, Aug 25, 2026
Server DRAM contract, 2026 about +270% more, forecast TrendForce, Aug 25, 2026
Server DRAM contract, 3Q26 +13-18%, forecast, capped by long-term agreements TrendForce, Jul 9, 2026
RDIMM bit supply, 2027 +15-20%, behind server CPU growth TrendForce, Jul 9, 2026
Server DRAM revenue, 2Q26 $75.58 bn, +53%; DDR5 over 90% of shipments TrendForce report abstract, Sep 2026
contract multiple, mid-2025 to end-2026:  1.64 x 3.70 = 6.07
a memory budget that bought 1,000 GB in mid-2025 buys 1,000 / 6.07 = about 165 GB
  at end-2026 contract prices, if the forecast holds
module spot, Nov 2, 2026:  RDIMM 63.3 / UDIMM 15.21 = 4.16
  -> a DDR5 RDIMM costs about four times a desktop DDR5 module per gigabyte

The 270% is a forecast, and who pays it matters. Several US cloud providers signed multi-year agreements that “restrict suppliers from raising prices for these clients”, and TrendForce expects that from the third quarter of 2026 “the primary source of server DRAM price increases will shift toward customers without LTAs”, with server DRAM prices rising every quarter through the second half of 2027. Mid-sized businesses meet the increase through the server makers they buy from. Buyers without a contract, and the businesses downstream of them, now set the price of last resort.

Buyers shrank memory to cope, some systems moving from 96GB and 128GB modules to 32GB and 64GB in the first half of 2026. HPE cut quote validity from 30 to 14 days in February 2026, though by August it was honoring quotes up to $1 million until shipment. Gartner expects business PC lifetimes to lengthen by 15% by the end of 2026. Without a long-term agreement, an older platform on DDR4 registered memory is worth pricing before a DDR5 refresh: compare DDR5 server, MRDIMM, DDR4 registered and Server RAM, and see why your server won’t take its maximum for the ceilings.

Long-term agreements turned a spike into a floor

In January 2026 Hankyung reported that Samsung and SK hynix were rejecting two- and three-year agreements in favor of quarterly contracts. By the middle of the year multi-year deals were being signed, with take-or-pay volumes, deposits and price floors for the sellers, and ceilings at or near 2Q26 prices for the largest buyers; by the end of October all three large makers had signed them.

Company Agreements Term Coverage Price terms Source
Micron 26 strategic customer agreements typically five years, 2026-2030, some into 2031; automotive three over 35% of revenue through 2030 take-or-pay; three-quarters of the expected revenue on a defined pricing framework, most of it in bands with a floor and a ceiling; the largest signed by June cap prices at the calendar 2Q26 market price; $32 bn of customer commitments, mostly cash deposits Micron, Jun 24 and Sep 30, 2026
SK hynix 14 customers, including leading cloud providers typically five years more than 50% of 2027 and 2028 production capacity prices move within a range agreed with customers; include deposits SK hynix, Oct 28, 2026; SK hynix and The Register, Jul 29, 2026
Samsung 10 customers, with 10 more in talks multi-year a target of 60-70% of production capacity by 2030 not disclosed Aju Business Daily via TrendForce, Oct 29, 2026
Winbond customers seeking terms beyond 2028 some negotiating for 2029-2030 not disclosed not disclosed MoneyDJ via TrendForce, Aug 2026
US cloud providers several agreements multi-year not disclosed restrict suppliers from raising prices TrendForce, Jul 9, 2026

TrendForce’s DRAM bulletin of October 7, 2026 describes the result: suppliers and cloud providers “have signed multi-year server DRAM LTAs, placing many of its bit supply under price-band mechanisms”, the rest being negotiated quarterly, “trading some price upside for a smoother, more predictable cycle”. On September 30 Micron put the contracted value still to be delivered under its agreements with a fixed price or a floor and a ceiling, counted at committed volumes and minimum prices, at about $150 billion, and said that “even at floor prices, we expect margins meaningfully above any prior cycle peak margins”.

The claim that “most” of Micron’s DRAM is contracted to 2030 runs ahead of the signed deals, which Micron put at over 35% of its revenue through 2030 on September 30, though it said on June 24 that it expects half or more of its revenue to fall under such agreements once the program is complete. A floor set at the top of a record cycle limits how far contracted prices can fall. Ceilings did not cap everything: TrendForce says HBM contract prices “could still rise by 70-140% in 2027”, and its bulletin of September 23 named the other consequence: “LTAs shrink negotiable supply as new fabs lag”.

Record revenue and margins at the suppliers

The suppliers’ own accounts show where the money went:

Company Period Revenue Margin A year earlier Source
Micron fiscal Q3 2026, to May 28 $41.46 bn 84.9% gross (non-GAAP); Mobile and Client unit 87% $9.30 bn; Mobile and Client 24% Micron, Jun 24, 2026
Micron fiscal Q4 2026, to Sep 3 $54.23 bn, against $49-51 bn guided 87.0% gross (non-GAAP) not given Micron, Sep 30, 2026
SK hynix 2Q26 KRW 79.32 tn 76% operating revenue +257%, operating profit +557% SK hynix, Jul 29, 2026
SK hynix 3Q26 KRW 104.62 tn 80% operating revenue +328%, operating profit +632% SK hynix, Oct 28, 2026
Samsung, chip division 2Q26 KRW 127.5 tn KRW 89.2 tn operating profit not given Samsung, Jul 30, 2026
Samsung, whole company 3Q26 KRW 195.3 tn KRW 107.4 tn operating profit not given; the quarter before, KRW 171.5 tn and 89.49 tn Samsung, Oct 29, 2026
CXMT 1H26 RMB 150.31 bn RMB 77.61 bn net profit revenue +873.64% ijiwei via TrendForce, Sep 23, 2026
Micron revenue:  41.46 / 9.30 = 4.46 times a year earlier
Micron gross margin (non-GAAP):  56.8% -> 74.9% -> 84.9% -> 87.0%

Micron’s fiscal 2026 revenue came to $133.19 billion, and it guided its fiscal first quarter of 2027 to $61.5 billion, plus or minus $1.5 billion (Micron, September 30, 2026). SK hynix’s third-quarter revenue rose 32% on the quarter and its operating profit 38% (SK hynix, October 28, 2026). Micron’s fiscal first-quarter results are due in mid to late December, on a date not yet announced, and the two Korean makers usually report their fourth quarters in late January.

New fabs take three to five years, and a cleanroom opening is not supply

Money is not the constraint: capital spending is rising, Micron’s from about $18 billion planned for fiscal 2026 to about $27 billion. SK Securities wrote in February 2026 that “capacity expansion remains restricted by a lack of available cleanroom square footage”, and Micron adds construction lead times, skilled trades, permitting and energy. TechInsights’ James Sanders told The Register in December 2025 that adding capacity takes about three years “if you’re rushing”, and that the big three are “looking at four or five years to ramp production at a new fab.” TrendForce wrote in July 2026 that “construction schedules, equipment installation, and raw material preparation will delay meaningful production ramp-ups until the second half of 2027”, with “substantial output contributions” not until 2028. Counterpoint wrote on November 5, 2026 that “major new fabs will not start production until 2028”, and Micron says output from a new fab “gradually becomes more meaningful starting a few quarters after initial output” (September 30, 2026). Each date below is the stage its source names: a cleanroom opening, equipment going in, a first wafer, or a ramp over several quarters.

Site Owner and product Milestone and date Source
ID1, Boise, Idaho Micron, DRAM first wafer output mid-2027, pulled in from 2H27 Micron, Jun 2026
ID2, Idaho Micron, DRAM first wafer output late 2028 Micron, Jun 2026
Tongluo, Taiwan Micron, DRAM; bought from PSMC for $1.8 bn, excluding production equipment meaningful shipments mid-2027; Phase 1 over 10% of Micron’s 4Q26 capacity (TrendForce estimate) Micron; TrendForce, Jan 2026
Hiroshima, Japan Micron, advanced DRAM expansion groundbreaking July 2026; initial output late 2028, for node transitions Micron, Sep 2026; Interesting Engineering ($9.3 bn); Tom’s Hardware gave $9.6 bn
M15X, Cheongju SK hynix, DRAM up to 70,000 wafers a month added in 2026 (press estimate); ramp accelerated JoongAng Daily; SK hynix
Y1, Yongin SK hynix, DRAM first cleanroom Feb 2027, brought forward from May; equipment from 2Q27 (press) SK hynix; JoongAng Daily
P4, Pyeongtaek Samsung, DRAM on its 1c node, the sixth 10nm-class generation over 200,000 wafers a month of 1c by end-2026, largely by converting lines (press) JoongAng Daily, Mar 2026
P5, Pyeongtaek Samsung, DRAM construction done 1H27; mass production late 2028; reported six months ahead (press) JoongAng Daily; TrendForce news desk, Aug 2026
China CXMT, DRAM estimates of 300,000 to 320,000 wafers a month now, 420,000 by 2027 the China section

Samsung’s P4 figure is mostly converted lines, adding bits through a finer node rather than new wafers, which is the general pattern:

2026 industry DRAM bit shipments:  up in the low- to mid-20s % (Micron, Jun 2026)
DRAM wafer capacity:  up 4.8% a year on average to 2030 (SEMI, Feb 2026)
1.23 / 1.048 = 1.17  -> roughly 17% more bits per wafer, a rough figure that is
                        already net of HBM's larger share of wafers

The first date on any fab announcement is the start of a ramp, not the arrival of supply. SK Group’s chairman Chey Tae-won said in June 2026 that SK hynix’s wafer capacity should double within five years and triple by about 2034, and “there is currently no way to move faster than this.”

China’s new capacity is real and mostly spoken for

CXMT’s share of DRAM revenue rose from 7.6% in the first quarter of 2026 to 9.5% in the second (TrendForce’s news desk, September 24). Counterpoint, whose count puts the second quarter at 10%, has it at 9% in the third and expects it to stay under pressure as rivals begin shipping HBM4 in the fourth (November 5, 2026). It raised about $8.6 billion in a Shanghai listing in July and on September 20 put its G5 process into mass production, claiming at least 50% more dies per wafer. On October 10 its president introduced a 4F² DRAM architecture, and the company plans server DDR5 RDIMMs based on it by the end of the year (TrendForce’s news desk, October 12, 2026, citing Yicai Global). Its capacity is estimated, not disclosed:

CXMT capacity estimate Who Date
about 300,000 wafer starts a month; over 600,000 if every project proceeds Reuters via Tom’s Hardware Aug 2026
about 320,000 now, 420,000 by 2027 Commercial Times via TrendForce Sep 2026
350,000 by end-2026 Citrini Research, a model Aug 2026

Most of it is spoken for at home. Institutional investors quoted by Commercial Times expect the new capacity to go mainly to China’s own AI and cloud build-out and to remain “insufficient to reverse the global supply-demand imbalance”, with no meaningful effect before 2027. The US controlled HBM exports in December 2024, and as of June 2026 CXMT was on the Pentagon’s 1260H list, though not on the Commerce Department’s Entity List. Chinese-chip memory was not cheap, either: a Lexar DDR5-7200 32GB kit using Chinese DRAM listed in China in August at 3,999 yuan, about $592, in line with comparable US kits. The former Samsung chip head Kye-hyun Kyung argued in May that prices could fall from the second half of 2027 if Chinese capacity delivers. Chinese supply is the most plausible early brake on prices and the least certain one.

When it ends: supply in 2028 at the earliest, prices undated

“When does it end” is three questions: when supply catches up with demand, when prices start falling, and when, if ever, they return to 2025 levels. The dated answers, in short:

  • TrendForce (July 30, 2026, and the Future of Memory and Storage conference in August): the gap widens in 2027, substantial new output arrives in 2028, and supply runs about 2% ahead of demand in 2028.
  • Micron (September 30, 2026): conditions “much tighter in calendar 2027 and 2028 than they were in 2026”, DRAM “supply constrained in both years”, no line of sight to balance, and price rises more moderate through its fiscal 2027.
  • The other suppliers: Samsung’s memory executive expects the shortage to be more severe in 2027 and to persist through 2028 (July 30, 2026); SK hynix’s chief executive called 2027 the “worst year” for supply (July 10, 2026); Nanya’s president expects prices to stay high until supply eases, possibly in the second half of 2028 (March 2026).
  • IDC (February and July 2026): its model “does not point to a reversion to 2025 pricing levels within the forecast horizon”, with relief not before 2028.
  • On price: nobody on the record dates a return to 2025 prices as such. AMD’s David McAfee said at Computex 2026 that DDR5 was about two years from normal pricing, and Bernstein’s model has one supplier’s price falling about 53% in 2028 from a 2027 peak, still about twice its 2025 level.

Suppliers and analysts alike place no meaningful relief before 2028: the consensus is no relief in 2026, probably none in 2027, and supply catching up in 2028 at the earliest. The dissent comes mostly from buyers, Acer above all, which expects PC prices to plateau in the first half of 2027 and then fall. The full forecast table is in buy RAM now or wait.

What would end it sooner, and what would make it last

The last supercycle shows what a real turn looks like: after TrendForce reported DRAM revenue down 18.3% in the fourth quarter of 2018, it put the first-quarter 2019 fall in PC DRAM contract prices at nearly 30% and in the average across all DRAM at more than 20% (March 5 and March 25, 2019), and only in January 2020 did it expect contract prices to turn flat to slightly up, about five quarters of decline. The triggers, with the signal to watch for each:

Direction Trigger Signal to watch Who says so, and when
Sooner consumer buyers reach their limit quarterly contract rises shrinking TrendForce, Jul 2026
Sooner 2026 demand was pulled forward 2027 orders; “channel restocking dims 2027 demand outlook” TrendForce bulletin, Sep 16, 2026
Sooner AI spending slows CSP capex guidance; negative free cash flow at some CSPs TrendForce, Jul 2026; analysts via The Register, Jul 2026
Sooner less memory per system server, phone and laptop configurations TrendForce, Jul 9, 2026; Micron, Jun 24, 2026
Sooner Chinese capacity delivers CXMT’s share and export status Kyung, May 2026; Acer, Sep 2026
Longer HBM4 and HBM4E raise the trade ratio HBM share of wafers, 30% by 2027 Micron; TrendForce, Jun 2026
Longer HBM repricing 2027 HBM contracts +70-140% TrendForce, Aug 2026
Longer cost per bit rising; contract floors supplier guidance Micron, Jun 2026

A slump in AI spending is the main route to an early end. TrendForce named the risk in July 2026: some cloud providers had reported negative free cash flow, and memory staying expensive through 2027 may affect their investment plans. A slump would lower spot and retail prices before contract prices, as the spring of 2026 showed on stock clearing alone, and contracted prices no further than their floors.

Efficiency is weaker than it looks: Google’s TurboQuant compresses the inference cache, not the model, and TrendForce expects cheaper inference to raise usage rather than cut memory demand (PCWorld, April 2026). Apple added 18% to the 13-inch MacBook Air against the roughly 80% TrendForce says a notebook needs to keep its margin, so margin is likely to be recovered before prices are cut, and at HP’s 35% memory share, halving memory’s price cuts the materials cost by 17.5%. When memory falls, a finished device falls later and by less. Apart from Chinese capacity, every path to an early end runs through demand falling, not supply rising.

Questions people ask, answered in brief

Why is RAM so expensive in 2026? The big three gave wafers to HBM and server DDR5 first, and a bit deficit of 1% to 2% met buyers who barely respond to price.

Why does HBM affect my desktop RAM? It is made on the same wafers, and a gigabyte of HBM takes roughly three gigabytes’ worth of wafer.

Why is old DDR4 sometimes more expensive than DDR5? End-of-life notices in 2025 cut supply. DDR4 chips cost about 32% more than DDR5 chips at spot on November 12, 2026, although DDR4 kits cost less per gigabyte at retail.

When will prices go down? Supply is forecast to catch up in 2028 at the earliest, and nobody on the record dates a return to 2025 prices. Forecasts by quarter are in buy RAM now or wait.

Prices dipped in the spring. Is it over? No. That was inventory clearing: the cheapest 32GB DDR5-6000 kit crossed $400 in August, and early October brought a plateau, not a fall.

Is used or DDR4 RAM a way around it? Partly. DDR4 kits cost less per gigabyte at retail, and one seller’s index shows DDR4 server memory falling; Trends follows both generations on this site’s listings, and is DDR4 still worth buying weighs the trade.

Which price number should I trust? The one whose layer and date match your purchase: a retail or listing price for a kit, never a chip’s spot price.

Where a figure here is a supplier’s, an analyst’s or a standard’s, the document is named with its date; where a figure is worked out here, the arithmetic is shown.

Related guides

Affiliate links:we earn from qualifying eBay purchases. eBay's live price is final. Full disclosureAffiliate disclosure:We are a member of the eBay Partner Network and earn a commission from qualifying purchases made through links to eBay on this site. Prices and availability are captured periodically and may have changed - the live price is always the one shown on eBay.